Reddington Construction is pleased to report that we are making good progress on our Crematorium project in Denham for our valued client Anoopam Mission.
This project is tailored to meet the needs of the Hindu community and once completed this will be the first ever purpose-built Hindu Crematorium in Europe.
Progress to date:
• Ground floor slab and Mezzaine level completed.
• Steel Frame completed.
• All drainage completed.
• All Roof decking completed.
• Crematorium roof including upstands completed.
• Main Hall roof completed.
• 90% of Brickwork completed.
• SFS completed.
• Car Park works 85% completed (By BDM
Construction)
• Mansafe systems on roof started.
• Protan insulation on roof 75% completed.
• Mass barrier ceiling install commenced along with partition walls.
• Mechanical services on roof commenced.
• M&E ductwork and copex for cables in walls commencing 5/5/26.
• All window Frames installed and glazing 85%.